Uneven Floor

M

Monkey Wrench

I'm a Plumber by trade but will often do a bit of tiling as part of a bathroom install when required. I'm currently working on a job in a 2m x 2.25m bathroom which requires me to install an 800 x 1700 floor mounted shower tray and tile approximately the remaining floor (just over 3 metres) with 500 x 300 porcelain tiles. I've tiled a number of floors before without a problem but this particular one is another matter.

The building is a converted barn that was totally gutted and converted into a house about 12 years ago and the flooring material is T&G chipboard flooring. The problem is that the floor drops about 23mm along the 2 metre length which is also the same length along which the floor mounted shower tray is to be mounted. The floor is also uneven along the 2.25 metre length but not nearly so extreme. Levelling the shower tray in itself is going to be a major problem but then, once its level, there's the problem of tiling. If I level the tray but follow the fall when tiling, the shower tray will appear higher one side than the other (along the length). Additionally, trying to tile such an uneven floor with such large tiles seems like a recipe for disaster. Is the only real solution to rip up the floor and start again or can anyone please recommend another solution ?

Thank you in advance for any helpful advice.
 
My advice would be to lift your P4/P5 boards & level out your joists then put back your P4/P5 & over sheet with Hardibacker 250. That would be my recommendation. If height is going to be an issue, you could replace your P4/P5 with 18mm WBP ply being sure to prime the underside & edges & fit additional noggins/dwangs. I'd go with option one first though
 
Thank you very much for the advice Bubblecraft.

Is levelling joists just a matter of fixing appropriate size wood shims along the top ? The other problem is the door threshold is on the "low" side of the 2 metre length so any levelling will automatically raise the door threshold accordingly (probably 23mm in this case plus the Hardiebacker and tile/adhesive).

Thanks again.
 
Thank you very much for the advice Bubblecraft.

Is levelling joists just a matter of fixing appropriate size wood shims along the top ? The other problem is the door threshold is on the "low" side of the 2 metre length so any levelling will automatically raise the door threshold accordingly (probably 23mm in this case plus the Hardiebacker and tile/adhesive).

Thanks again.

The easiest way is to lay timber shims on top to the desired thickness to bring the floor level. I would space these every 600mm & put a timber noggin no less than 47mm x 125mm (5" x 2") up to the level of your shims.

Unfortunately in some cases, a step into the bathroom cannot be avoided. Finish off with a floor trim with a vertical tile up to it.
 
The easiest way is to lay timber shims on top to the desired thickness to bring the floor level. I would space these every 600mm & put a timber noggin no less than 47mm x 125mm (5" x 2") up to the level of your shims.

Unfortunately in some cases, a step into the bathroom cannot be avoided. Finish off with a floor trim with a vertical tile up to it.

Thanks again Bubblecraft.

The joists are running across the fall and not along it, does that make a difference ?
 
Thanks again Bubblecraft.

The joists are running across the fall and not along it, does that make a difference ?

Yes. That should make it a little easier. Just run them along the top of your joists to the height required. Just make sure your shims are no ness than 2" wide. You'll still need to fit your noggins every 600mm to the height of your shims.
 
The other problem is that two of the walls have just been replastered and the board is tucked very snuggly underneath !
 
If you find it difficult to remove the boards without damage to the walls, use a reciprocator to cut them out. This way you can cut them tight to the wall. Depending where your joist hits, you may have to add an additional joist there too to give you a fixing again. If a lip of flooring is not going to be an issue say you will be boxing in a pipe chase, use a circular saw to cut them out. The flooring that is left will be the width of your guard. This is a far quicker method. Mind & set your guard to the thickness of your flooring so you don't hit any pipes or cabling.
 
Thank you very much for the advice Bubblecraft.

Is levelling joists just a matter of fixing appropriate size wood shims along the top ? The other problem is the door threshold is on the "low" side of the 2 metre length so any levelling will automatically raise the door threshold accordingly (probably 23mm in this case plus the Hardiebacker and tile/adhesive).

Thanks again.

another way of constructing the raised area would be to rip some 18 mm ply in to strips equal to joists ( about 8 inch ) , screw them each side of the joist to the new height and then insert smaller packers between the ply on top of joists. Hire a laser level or if you have large normal level then this will do.
note: get your ply wood from bnq and get them to rip it down, they also have local price match policy and will beat rivals by 10%.
also, use plenty of screws!
 
If you find it difficult to remove the boards without damage to the walls, use a reciprocator to cut them out. This way you can cut them tight to the wall. Depending where your joist hits, you may have to add an additional joist there too to give you a fixing again. If a lip of flooring is not going to be an issue say you will be boxing in a pipe chase, use a circular saw to cut them out. The flooring that is left will be the width of your guard. This is a far quicker method. Mind & set your guard to the thickness of your flooring so you don't hit any pipes or cabling.

Thanks again for the excellent advice Bubblecraft.

I guess there's little point in trying to pull the boards completely out from the walls anyway as, after the leveling, the edges would have to be trimmed flush to the wall as they certainly wouldn't tuck back into where they originally came from ! If I leave a lip of flooring (probably a couple of inches), I guess I'll have to try and fill it with some shims before laying the Hardiebacker and then tiling !
 
another way of constructing the raised area would be to rip some 18 mm ply in to strips equal to joists ( about 8 inch ) , screw them each side of the joist to the new height and then insert smaller packers between the ply on top of joists. Hire a laser level or if you have large normal level then this will do.
note: get your ply wood from bnq and get them to rip it down, they also have local price match policy and will beat rivals by 10%.
also, use plenty of screws!

Thank you charlie1, when you say "equal to the joists" (about 8 inch), I assume you mean the depth of the joist ! Should these also be spaced at 600mm ?

What do you mean by "get B&Q to rip it down" ?

Thanks again.
 
Thank you charlie1, when you say "equal to the joists" (about 8 inch), I assume you mean the depth of the joist ! Should these also be spaced at 600mm ?

What do you mean by "get B&Q to rip it down" ?

Thanks again.

Yeah. What Mark meant is that if your joists are 6" x 2", have your ply ripped into 6" lengths. If you go to B&Q, get your self 8' x 4' sheets & B&Q will rip them into 6" lengths (providing your nearest store is a warehouse & has a panel saw) If you have a Trade Point card, your cuts are free of charge. So 6" x 8'. You get roughly 8 lengths to a sheet @ 6". This wouldn't be spaced at 600mm but running the full length of both sides of your joists then fill in the cavity between the sheets of ply on top of your old joists
 
Yeah. What Mark meant is that if your joists are 6" x 2", have your ply ripped into 6" lengths. If you go to B&Q, get your self 8' x 4' sheets & B&Q will rip them into 6" lengths (providing your nearest store is a warehouse & has a panel saw) If you have a Trade Point card, your cuts are free of charge. So 6" x 8'. You get roughly 8 lengths to a sheet @ 6". This wouldn't be spaced at 600mm but running the full length of both sides of your joists then fill in the cavity between the sheets of ply on top of your old joists

Ok, understood. Whats' the best way of filling the cavity ? Cut down bits of wood ?
 
Yeah. What Mark meant is that if your joists are 6" x 2", have your ply ripped into 6" lengths. If you go to B&Q, get your self 8' x 4' sheets & B&Q will rip them into 6" lengths (providing your nearest store is a warehouse & has a panel saw) If you have a Trade Point card, your cuts are free of charge. So 6" x 8'. You get roughly 8 lengths to a sheet @ 6". This wouldn't be spaced at 600mm but running the full length of both sides of your joists then fill in the cavity between the sheets of ply on top of your old joists

thanks bc, that's exactly what i mean.
 
yes, smaller packers made from wood, glued and screwed.

Thank you charlie1. Assuming I used a circular saw, what would you suggest I did with the lip left around the edges with regard to laying the Hardiebacker and tiling ?
 
Got you, only option is to create a step (about 50mm) using the porcelain or timber, i don't think there is any metal ones out there for that drop
 
Get it as tight as possible to the walls, do the depending which way the joists are running, you may need to add more noggins to support the new height.
 
Your raising the whole floor?

The floor drops about 25mm from the door to the window (opposite the door) and the joists run from the door to the window.The distance from the door to the window is 1.98m so I guess the whole floor will need to be pulled up to level it properly. I was intending to use a circular saw as I don't have a reciprocating saw, but this would then leave an edge of board around the wall the same width as the guard on the circular saw.
 
if the floor joists are spaced at greater than 300mm c/c then new noggins should be spaced at 300mm c/c before relaying the floor.
Steve
 
The floor drops about 25mm from the door to the window (opposite the door) and the joists run from the door to the window.The distance from the door to the window is 1.98m so I guess the whole floor will need to be pulled up to level it properly. I was intending to use a circular saw as I don't have a reciprocating saw, but this would then leave an edge of board around the wall the same width as the guard on the circular saw.

As I've stated in one of my posts, you could put boxing around where the floor has the left over P4/P5. If not, you could use your circular saw first & cut the remaining board off with a normal handsaw. Just drill 4 or 5 18mm holes with a speed bit starting from the corner & use your handsaw to do the rest. It's a bit more work but would eliminate the need for boxing.
 
Could you not just make up the lip with offcuts of Hardibacker if you cant cut tight enough
 

Advertisement

Thread Information

Title
Uneven Floor
Prefix
N/A
Forum
Canada Tile Advice
Start date
Last reply date
Replies
24

Thread Tags

Advertisement

Tilers Forums Official Sponsors

Thread statistics

Created
Monkey Wrench,
Last reply from
destroyer2813,
Replies
24
Views
11,687

Thread statistics

Created
Monkey Wrench,
Last reply from
destroyer2813,
Replies
24
Views
11,687
Back