Do we comission a wet ufh system floor that has a timber ply base like an anhydrite screed.

Bring up 5 degrees a day to maximum waterflow temp for 5 days then gradually back down.

Have done many anhydrites but first timber.

Many Thanks

Kevin
 
Not sure what you mean Kev... is this a timber floor to be laid or wet heating under timber sub-floor..?
 
I have re-read and it is confusing.

The heating pipes have been encased in between the joists then boarded over with ply to the joists then overboarded again.

Having never tiled to ply before was wondering if the intial commissioning of the ufh before tiling is the same as when it is a solid sub base.

Cheers.

Kevin
 

Advertisement

Thread Information

Title
Timber wet ufh
Prefix
N/A
Forum
Canada Tile Advice
Start date
Last reply date
Replies
3

Advertisement

Tilers Forums Official Sponsors

UK Tiling Forum; UK

Thread statistics

Created
kaharrison9,
Last reply from
kaharrison9,
Replies
3
Views
1,443

Thread statistics

Created
kaharrison9,
Last reply from
kaharrison9,
Replies
3
Views
1,443
Back