N
Nick Jones
I'm sorry, but what has all this got to do with the fact that I want to get an independent and impartial report on the work.What joint width did you specify . What was the timescale . Did he originally want longer . Ie washed he pushed or not .
I think there is more truth to come from this but don't get me wrong I'm not saying it is a good job but there may be mitigating circumstances that may affect you that we haven't heard .
However - as to joint width.
He originally asked me which way did I want the floor tile to run. I said that I wanted the long side of the tile (60 x 30) to run the short way in the room, to make it look bigger.
He then said that I knew that the wall tiles wouldn't match. I asked for clarification - he said that the joints on the vertical wall tiles would not match with the joints on the floor tiles. I referred him to the "visualiser" from Topps Tiles, plus several example of where the joints did match.
I told him that the joints were to match. He accepted this.
After he had laid the floor tiles, he asked me what width did I want the joints on the wall tiles.I said the same as the floor.
He showed me the spacers (5mm ?) he used on the floor, and the (4mm ?, but I don't think it was 3mm) spacer he would have used on the walls. I said that the joints had to be the same, otherwise it would not match. He accepted this without any further comment.
The wording on the grout says it is good for joints between 1mm and 20mm, and I have no doubt that there will be numerous examples of a 5mm joint on wall tiles.
And if he thought 5mm wall joints were excessive, then what about the 10mm joint he had between the edge of the mosaic and the corner of the walls.
Timescale is what he said - start on Monday 8/1/18, finish on Friday 19/1/18. I booked those 2 weeks in a B & B nearby, so that I'd be out of the way. Let me remind you - he had another job booked to start om Monday 22/1/18, so it was HIS timetable. When he had not finished my job, I had even said that he had to concentrate on this next job, not on mine, and that my job would get done. If I had a WC that worked, and I could always wash myself at the kitchen sink (because the shower area was not finished and waterproofed), so I wasn't going to pressure him - he's a work colleague and I'm not going to cause him problems and any hassle.
Frankly, I do object to the inference that I've caused the problem.
If he misforecast the time needed for the project, that is down to him.
If using a 5mm wall joint between tiles was going to cause a problem, then it should have been mentioned - although there are numerous instances where this is not a problem.
He did the work - badly.
The end result shows.
He is of the opinion that it is a good job, except I do not agree. And I think, that the general consensus is that it is not a good job.
However, could I just say that what I am after is an independent, impartial report on this work, detailing what is wrong (and if there is something right, then stating that also) and suggesting a way forward.
I have my own thoughts, obviously.
