Hello,
I'm renovating my 2nd floor master bath. I'm about to lay down tile in three areas... on the shower floor first, then the his and her side bathroom floors, and finally the shower walls - in that order.
My question is...
Should i grout immediately after each tiled area's mortar it set/dry (24 to 48 hrs) or can i wait till after all the tile areas are set/dry before grouting?
Thanks,