Guys, this is not really a tiling question but a friend has the following problem and I wondered if any of the screeding experts eg ajax? had a view on it.
This is her situation:
Hi, I'm looking for some advice on our engineered wood floor which we've recently had laid by our builder.
We've had a ground floor extension built with a block and beam floor. On top of this they've laid Celotex insulation boards, a wet underfloor heating system and then sand and cement screed, approx 70-80mm thick. 9 days after laying the screed (the weekend before xmas), the builder insisted it was dry enough to lay the engineered walnut floor we had purchased. This was laid throughout the downstairs and over the UFH. It was then left for 3-4 weeks while they completed other jobs, with plastic sheeting protecting the wood.
This Friday the manifold for the underfloor heating was connected and the floor heated for the first time. They left it on full whack for 24 hours, at which point we uncovered the floor to find it wet and rippled all over; it has also lifted in places. We think this is due to the screed not being left to dry for long enough. Our builder denies this, saying the drying time is shorter for a block and beam floor. We had no heating downstairs when the screed went down and it was freezing outside most nights.
Has anyone experienced this problem at all? Is there anything that can be done to improve the appearance of the wood or are we going to have to ask him to replace that part of the floor? We are concerned that the unaffected part of the floor may get damaged where they key in the planks, not being professional floorers. Are we within our rights to ask him to get a pro in?
This is her situation:
Hi, I'm looking for some advice on our engineered wood floor which we've recently had laid by our builder.
We've had a ground floor extension built with a block and beam floor. On top of this they've laid Celotex insulation boards, a wet underfloor heating system and then sand and cement screed, approx 70-80mm thick. 9 days after laying the screed (the weekend before xmas), the builder insisted it was dry enough to lay the engineered walnut floor we had purchased. This was laid throughout the downstairs and over the UFH. It was then left for 3-4 weeks while they completed other jobs, with plastic sheeting protecting the wood.
This Friday the manifold for the underfloor heating was connected and the floor heated for the first time. They left it on full whack for 24 hours, at which point we uncovered the floor to find it wet and rippled all over; it has also lifted in places. We think this is due to the screed not being left to dry for long enough. Our builder denies this, saying the drying time is shorter for a block and beam floor. We had no heating downstairs when the screed went down and it was freezing outside most nights.
Has anyone experienced this problem at all? Is there anything that can be done to improve the appearance of the wood or are we going to have to ask him to replace that part of the floor? We are concerned that the unaffected part of the floor may get damaged where they key in the planks, not being professional floorers. Are we within our rights to ask him to get a pro in?