Time to lay anti fracture mat

R

RicoBarry

I’m trying to find out out how long it should take to lay Tilemaster antifracture mat.
The area is 80m2 and has been levelled with self levelling compound.
Many thanks
 
4 rolls, so if it's an open area, maybe 2 hours.
If it's all ins and outs, multi room - perhaps all day.

If you've never fitted TM mat before, maybe even longer!

Or are you a customer "checking out" a quote?!
 
Hi
I’m a customer trying to work out why it has taken so long to lay and stick down. Unfortunately I am away with work a lot and can’t see what’s going on. But 5 days to prep!!! Bearing in mind 2 of them self levelled the 80m2 in 3 hours beforehand. (On a Saturday when I was around).
Your thoughts on this would be appreciated.
Many thanks
 
Thanks for getting back to me.
House being renovated, UFH and screed on top, followed by self levelling compound and the anti fracture mat. 5 x £*** to lay the mat alone! Is the bill that’s come in.
£*** for 2 x 3 hours to lay the self levelling compound.

image.jpg image.jpg
 
Last edited by a moderator:
Did you have a written quotation agreed before they started? If not, it sounds like you need a clear and honest discussion before they carry on - for the sakes of everyone involved.
I can't comment on prices in the open forum, but it does look like they've made a good job of the prep, which usually bodes well for the end result.
 
Did you have a written quotation agreed before they started? If not, it sounds like you need a clear and honest discussion before they carry on - for the sakes of everyone involved.
I can't comment on prices in the open forum, but it does look like they've made a good job of the prep, which usually bodes well for the end result.
Written quote for laying tiles bu
 
Written quote for laying the tiles but a day rate for prep. I know you can’t talk prices but it shouldn’t take 5 days, should it?
 
Without knowing exactly what was done, it's not fair to say a definite no. But assuming it was straightforward, I'd expect to install that amount of mat, on my own, in two days max.

But we've all turned up to jobs where everything needs moving, other trades leave muck all over the floor, water wasn't available, etc etc...

What are they saying to justify 5 days?
 
Maybe im slow compared to
Without knowing exactly what was done, it's not fair to say a definite no. But assuming it was straightforward, I'd expect to install that amount of mat, on my own, in two days max.

But we've all turned up to jobs where everything needs moving, other trades leave muck all over the floor, water wasn't available, etc etc...

What are they saying to justify 5 days?
I would allow 2 days I work on about 5metres an hour for matting although not had much experience with tilemaster .
 
Maybe im slow compared to

I would allow 2 days I work on about 5metres an hour for matting although not had much experience with tilemaster .
It's not the easiest to install. In fact it's pretty horrible, but assuming it's prepared well, comb and roll... Its four 20m rolls. I see they've used sheets which would be slower in any case...
 
It's not the easiest to install. In fact it's pretty horrible, but assuming it's prepared well, comb and roll... Its four 20m rolls. I see they've used sheets which would be slower in any case...
I was wondering about that not being familiar with tm antifracture was thinking have they cut into short lengths for some reason .
 
2 days for me as well to lay that, but like impish said, it depends on the situation, the work environment, the amount of other stuff that have had to do before they can lay the mat, etc. Are you sure there isn’t some crossed wires ?
 
Hi thanks for all your responses.
House and floor was completely clear, no other trades and no other reasons for delay.
Thanks for the info, seems most of you are all in line with 2 days.
It was over 3 days, with 1 tiler working on prep for all 3 days and the other for 2 days (5 in total).
 
Hi thanks for all your responses.
House and floor was completely clear, no other trades and no other reasons for delay.
Thanks for the info, seems most of you are all in line with 2 days.
It was over 3 days, with 1 tiler working on prep for all 3 days and the other for 2 days (5 in total).
What do you mean working on prep .
 
Sorry I couldn’t lay 80 square metres of matting in 2 hours no matter how big and square the room was!!
 
Thanks for all your responses. Old tiler removed and he’s £400 down on this weeks invoice! Still claims he wasn’t taking the ****! But was pretty easy getting him to reduce bill. He’s happy as he’s off to rip someone else off next week....
 

Advertisement

Advertisement

Tilers Forums Official Sponsors

UK Tiling Forum; UK

Thread statistics

Created
RicoBarry,
Last reply from
Simon Dale,
Replies
27
Views
11,808

Thread statistics

Created
RicoBarry,
Last reply from
Simon Dale,
Replies
27
Views
11,808
Back