Firstly, at the junction where the tiled floor meets the tiled wall, what is tiled first? Wall before floor or vice versa? Does it matter? Sealing the junction with grout or silicone?

Secondly, roughly how long does it take the tanking system to go off? Not decided which brand we're using yet but some require two coats. Roughly how long will an average system take to dry before the second coat can go on?

I thank you in advance :)
 
P

p4ulo

I always like to tile the floor first then tile down onto it, leaving a few mm between which you then sealant.
However, a job I'm doing "slow-time" at the moment for a mate is walls first cos the floor ain't fitted properly yet....I'm my mind it's harder this way around cos you can "hide" the floor tile cuts with the wall tiles if you need to!?
Tanking systems, should be all done and dusted within an afternoon / morning.
They are usually re-coatable after a few hours, some go off much quicker.
 
O

Old Mod

Ardex WPC is very easy and quick to do.
It's a popular choice with guys on here.
Walls tiles down on to floor where possible.
If u leave your bottom cut out till floor is tiled then u can still tile walls first.
But it's not always possible to do.
But if you're bonding all wall joints with floor joints right through and back up otherside, just be aware of your joint line.
 

ANDY F

TF
Reaction score
47
Points
498
Location
Macclesfield
I also note that tiles need to be cut diagonally to follow the fall of the pre-formed shower tray. Is it as simple as cutting the tile and then skimming off the end what is required to form a grout joint? If you wanted a 3mm joint, take 1.5mm of both sections of the tile?

Wet-Room-Sloped-Floor[1].jpg
 
O

Old Mod

I also note that tiles need to be cut diagonally to follow the fall of the pre-formed shower tray. Is it as simple as cutting the tile and then skimming off the end what is required to form a grout joint? If you wanted a 3mm joint, take 1.5mm of both sections of the tile?

View attachment 78304
If u use a wet saw for your cuts, this will form your grout joint.
 

Reply to Advice On The Finer Detail Please in the Tanking and Wetrooms Forum area at TilersForums.com

There are similar tiling threads here

    • Like
Bathroom floor. I would be grateful for advice on how to prepare my bathroom sub floor ready for...
Replies
1
Views
435
I had a small leak in the main water line before the stop tap in my 1950s house. The copper pipe...
Replies
1
Views
616
Good morning all. After a little advice. I'll post pictures a bit later. However.... The...
Replies
6
Views
787
Hi! I'm looking for some advice, I have laid some SLC (Mapei 1210) in our conservatory in...
Replies
5
Views
571

Advertisement

New Tiling Questions

Replies you've not seen

Top