Extension UFH combined with existing floor

Tilers Forums Official Sponsors

Hi.

I'm currently building a single floor rear extension that will have UFH, I'm pretty confident about the extension UFH. 100mm insulation, 70mm screed, etc. My question is about the existing kitchen and dining room that will become one open plan space as part of the extension.

The make up of the existing floor is 60mm of screed on a block and beam floor. I would like to install UFH in this existing area also. Is it worth/possible to take up the existing screed and install a insulated solution option B, or just go for an overlay solution option A?

upload_2017-10-14_0-34-31.png


I would prefer option C if possible due to it being insulated and introduces less of a height difference with the rest of the house. Any special considerations needed for option C?

Thanks in advance.
 
Last edited:
Option b, every time .
Rip up the old floor and screed right through.
It's not perfect with 25mm insulation, but it's the best that you can get with the limitations of floor build up.
Also for tiling, it makes a continuous floor. With no differing rates of expansion.
 
Option b but at that thickness of screed you would have to use a poured screed but I'm not sure if it ok at 40mm @Ajax123 is your man to answer that .
 
Thanks both.

I was planning on using and poured/liquid screed anyway. Is there an optimum insulation/screed ratio as I am height limited?

Also am I able to use the same pipe throughout or should the loop in the existing maybe user smaller pipe?

Cheers.
 
If you use Gypsol HTC anhydrite screed over a 16mm pipe you can lay it at a depth of 41mm from the top of the insulation to the top of the screed. This screed is specifically designed to offer very thin depth and very high thermal performance to make the underfloor heating system as efficient as possible. Typically it increases the coefficient of performance for the heating system by some 25%.

If you intend to use a cement based screed then the minimum depth would be 65mm. This means that the minimum depth is over the top of the pip so with a 16mm pipe you would need 81mm. Most people compromise at 75mm...it may still crack.
 
That's great thanks. Is there a maximum depth? The new extension screed will be about 70/80mm to make it level with the existing floor.
 
That's great thanks. Is there a maximum depth? The new extension screed will be about 70/80mm to make it level with the existing floor.
If you wnted a liquid screed you could just put deeper insulation into fill the void. This might allow you to use polystyrene instead of foil backed PIC thus saving quite a bit of money per m2
 
Hi all.

I eventually went for a cementitious screed . It was pumped in February. I'm only now in a position to commission the UFH and lay tiles.

Unfortunately some cracks have developed in the screed. Some only hairline, others maybe 2-3mm wide. They developed slowly in the first few months after installation and haven't really changed since then. These cracks are both in the existing section of the house, block and beam floor. And also in the extension, solid slab.

1. Should I be concerned with these cracks?
2. How do I stabilise them?
3. Am I OK to tile directly on the screed with porcelain tiles? 600mm x 300mm

Many thanks all.

upload_2018-8-21_22-31-24.png


upload_2018-8-21_22-31-50.png


upload_2018-8-21_22-32-12.png
 

Advertisement

Thread Information

Title
Extension UFH combined with existing floor
Prefix
Forum
Tiling on Underfloor Heating
Start date
Last reply date
Replies
16

Thread Tags

Tags Tags
floor ufh

Advertisement

UK Tiling Forum

Thread statistics

Created
MarkUFH,
Last reply from
MarkUFH,
Replies
16
Views
9,748

Thread statistics

Created
MarkUFH,
Last reply from
MarkUFH,
Replies
16
Views
9,748
Back