Hi Quick bit of advice, just purchased a BAL Waterproofing Kit for a shower (WP1) in a tub, didn’t have any instructions so I have looked up on BAL website, The instructions seem a little confusing or I may be misunderstanding the terminology :

The walls this is to be applied are for a shower and are new Moistureshield Plasterboard, with 2 internal corners
I have been supplied with Waterproofing which is in a tub and some reinforcement for the internal corners
And from the instructions this is my understanding of what I need to do :

  1. Tape all edges (do I add the corner reinforcement at this point ?)
  2. Apply skim coat of BAL adhesive
  3. Prime with APD
  4. Brush on WP1 in corners and taped edges (or do I add corner reinforcement here ?)
  5. Apply 2[SUP]nd[/SUP] coat of WP1 to corners and tape (how long do I leave to dry ?)
  6. Apply 2mm thick coat to complete area
  7. Leave to dry for 24 hours before tiling

Have I understood currently and when do I apply the corner reinforcement ?

Thanks
AH666
 
Info from Bal..


APPLICATION/USAGE
Do NOT use in temperatures below 5°C or in damp conditions.
Usage procedure
1. Prime all surfaces with BAL PRIME APD and allow to dry
(15-30 mins).
2. Using a suitable brush or steel float, apply
BAL WATERPROOF COATING at:
– Internal and external corners of walls/partitions
– Wall junctions with bases/upstands/columns
– At pipe penetration points/drainage channels/outlets
– Junctions of different bases/background materials
– Cracks and joints in background/base
3. Reinforce with BAL POLYESTER TAPE.
4. Apply second coat of BAL WATERPROOF COATING over
the BAL POLYESTER TAPE.
5. Using brush or steel float, apply BAL WATERPROOF
COATING to primed walls at a max. 2mm thickness.
6. Apply BAL WATERPROOF COATING to primed floor.
7. Reinforce with BAL POLYESTER MATTING (may be cut
to correct size with scissors).
If applying in heavy duty wet areas (e.g. communal showers
and industrial wet process areas) and/or where some vibration
or deflection in the base may be expected (e.g. timber bases):
8. Bed matting into coating and apply a second layer of
BAL WATERPROOF COATING over top.
9. Allow membrane to dry for min. 24 hours before tiling.
 
And if you're using this for the first time i'd suggest using a brush to apply your costs and not the skim option. It's essential you get a good even coat.
 
And wear gloves or you'll spend days peeling it off your hands. I use a block brush to apply this stuff.
 

Advertisement

Thread Information

Title
BAL Tank Kit
Prefix
N/A
Forum
UK Tiling Forum
Start date
Last reply date
Replies
4

Advertisement

UK Tiling Forum

Thread statistics

Created
ah666,
Last reply from
jlktiling,
Replies
4
Views
5,021

Thread statistics

Created
ah666,
Last reply from
jlktiling,
Replies
4
Views
5,021
Back