Terrazzo flooring in supermarkets

UK Tiling Forum; Established 2006

Welcome to the UK Tiling Forum by TilersForums.com, built in 2006 by Tilers, run by Tilers.

View all of the UK tiling forum threads, questions and discussions here.

Tilers Forums Official Sponsors

As Gary and Barry, ( sounds like a double act):lol: Slurry bond to sub-floor, semi-dry,then slurry bond to back of tile. Each tile fixed individual to a tingle line.:thumbsup:
did you use a 10 bob note to steady your tingle Phil?:smilewinkgrin:
 
Phil you should be careful...in my experience a tingle can sometimes lead to a mingle!

Pebbs
 
well i just watched the film mike, it's funny how you can be irritated by other peoples working way's , when he was laying the two tile section it was all dusty/dry he splashed a bit of cement slurry in from a jug then the screed, he should have thoroughly cleaned out then wet the hole with a jug of water and left it to soak -in then slurry/screed as this would have given a much stronger bond, but they where realy relying on the resin grout to set the repairs for speed IMO

I thought the same thing Tom, it all looked very messy and very hit and miss to me. It also said "this floor will be in use in a couple of hours". Well, the cement / screed bond wouldn't have gone off in a couple of hours, so they must be relying on the resin grout bond to hold the plates firm.
 
I worked along side some of the best terrazzo men in my time, and that vid was spot on , as far as the fixing method was concerned, but it was a patch up job. A good terrazzo man can lay 100m2 per day, every day, a good labourer is essential imo. The method is the same on a new floor. A leg is brought from the first course,laid perfectly straight and level, then a tingle line is fixed, so you repeat again and again. The method is tried and tested, as we have said the subfloor is given a slurry bond coat, ( traditionally pure portland cement) then semi-dry mix 4:1 sand and cement. then either a slurry bond over the semi-dry mix, or the back of the tile brushed with slurry.

All the terrazzo men I know never kneel down, but fix from a standing position.The old polishing machines were called Ellis, the newer ones are Terrco's. The polishers job is made easy or hard by the skill of the fixer. Hope I don't get a lashing from the terrazzo lads who are more up to date than me.:thumbsup:


Thanks Phil. I wish I could find a video showing how they do it on a large scale and at real speed (as opposed to just a repair). I assume that the chap in the clip had dug out half the screed with his pneumatic drill, and that when laying a whole terrazzo floor from afresh it is not required to put down 2 - 3 cms of semi dry sand and cement and then tap each tile with a mallet, lift, add more screed, lay again and tap again? Otherwise I cannot see how they can get a good work rate, or ensure a level floor, if they are putting down thick screed on every row???

Also, fixing from a standing position must be incredibly hard on the lower back and knees after a while???

It definitely looks like a very skilfull trade.
 
Phil pretty much has it spot on here.I used to work for the biggest terrazzo company in the country as a labourer for terrazzo men. There were 2 labourers to 1 tiler because that is how physically hard the job is.

The tiler would set out the job with the help of a site engineer to get the correct levels and pattern set out.Then it was back breaking work all day.

If we didn't have ready screed mix we would have 1 labourer on the mixer (mixing screed all day) and 1 labourer and 1 tiler on the "line". The concrete floor was covered in a mixture of Bal Bond and water and swept all over with a brush to keep the floor wet but not saturated.
The mixing labourer would wheel barrow the screed in piles as you were working backwards. The other labourer would be on the "shovel" shoveling the screed down from 1 end to the other spreading the screed bed for the tiler.The tile line would be about 40 tiles long (300mm tiles)

The tiler used a screed lat to get the perfect bed for laying the tiles, and spread from one end to the other behind the labourer shoveling in.
We had big blue tubs which we mixed 8 buckets of water to 4 bags of cement (slurry) stirred with a mixing paddle. The labourer took half a bucket of the slurry and poured it along the screed bed from one end to the other. He would then put the tiles down for the tiler to tap down with a rubber mallett. The tiler used a string line like brickies do to get the tiles levelish, some tilers used very very strong sea fishing line as the string lines had a habit of snapping when they got wet.

The grouting we mixed the same way as the slurry 2 buckets of water to 1 bag of "white" cement depending on how big the area is. Big squeegies were used like brushes to spread the grout and fill the joints and this was done through out the day until the joints were full.

You would then have your polishers who did the grinding and polishing with terco machines to get a glass like finish.
As far as doing 400 meters a day ? nah i don't think so matey. more like between 150 and 200 meters a day with out any hold ups on site.

All in all its a back breaking very physically demanding job and warrants more money than the workers get. We got payed 60% tiler 40% labourer of the total price work.
 

Advertisement

Thread Information

Title
Terrazzo flooring in supermarkets
Prefix
N/A
Forum
UK Tiling Forum
Start date
Last reply date
Replies
16

Thread Tags

Advertisement

UK Tiling Forum

Thread statistics

Created
Mike Mike,
Last reply from
tony4173,
Replies
16
Views
9,226

Thread statistics

Created
Mike Mike,
Last reply from
tony4173,
Replies
16
Views
9,226
Back