Hi all,

Just after opinions from you guys.

I have been doing a friends bathroom refit as a favour and to also develop my experience etc.


I have done five solid days so far.


Remove old suite
Hacked walls back to brick and to old stud wall.
Reboarded walls and ceiling.
Drilled new basin waste and boxed in.
New feeds for basin, pan and bath (all hidden in walls)
Stud/partition wall with shower feed and niche
Plasterer has skimmed ceiling and walls.
Electrician fitted 3 new downlights
Painted walls and ceiling
Fitted bath
Tanked bath
Tiled 50% of walls

Left to do :
Construct bath frame and tile it.
Finish wall tiles (approx 4sqm)with boxing section and window wall.
Backer board floor and tile floor.
Grout all.
Fit shower, screen, toilet, basin and accessories.


I’m hoping another 3 days max. Does this about right in terms of days worked ? I am not a professional although I always strive for a good finish and therefore can take my time.

The whole thing has been an eye opener as I want to get it sorted as soon as possible but don’t want to burn myself out

Cheers all
 

Coop5

TF
Reaction score
3
Points
113
Yes that’s what I’ve found, planning the niche took a good few hours alone.

I just wanted some average times to see how I compare. It’s only a small room but again that has caused its own issues
 
Q

Qwerty

Sounds like you're making decent progress but every job is different. Some need alot more prep than others, some have perfect tiles and easy layout. All depends on the job.
 

jobdone

TF
Esteemed
Reaction score
182
Points
533
Location
Chobham
Each job has to be judged on time on an individual basis. Level of finish, type of tile, wall construction, first second or third floor stairs add time. Parking all these thing have to be taken in to consideration
 

Boggs

TF
Esteemed
Arms
Reaction score
4,729
Points
1,118
Location
Uk
Sounds like good progress to me.
 

Andy Allen

TF
Esteemed
Arms
Reaction score
18,311
Points
1,318
Location
Gloucester
Me and my plumber will normally take 6 to 7 days on a full refit...
If your on your own doing everything then 2 to 3 weeks wouldn't be unreasonable.
 

Reply to Friends bathroom refit timescales in the Canada Tile Advice area at TilersForums.com

There are similar tiling threads here

    • Like
Bathroom floor. I would be grateful for advice on how to prepare my bathroom sub floor ready for...
Replies
1
Views
414
Hi! I'm looking for some advice, I have laid some SLC (Mapei 1210) in our conservatory in...
Replies
5
Views
549
Hi all! Just wondering what the best advice is for book-keeping? Been self employed now for a...
Replies
1
Views
558
Good morning all. After a little advice. I'll post pictures a bit later. However.... The...
Replies
6
Views
752
Hi all. Just wanting some advice and wondering what the pros in here are using nowadays for...
Replies
2
Views
531

Advertisement

New Tiling Questions

Replies you've not seen

Top