Hi folks,
I turned up to start the job and began ripping up the existing quarry tiles to find the concrete bed of the steps hanging in about 2 inch of water, with pitholes in the bed about 4 inch deep - full of water! It rained the whole time i was there lifting the existing tiles.
Told the customer that this is not good for tiling - suggested we get the excess water off, allow the bed to dry out and begin prepping the surface - as in filling and levelling the bed, and shuttering the tread and rises to the same depth. This work was intermittent based on the weather, i.e is was leathering down most of the time i and didnt want to drop concrete or leveller under such conditions. All this time, i covered the bed and steps down with tarp to protect it from the rain as best i could.Anyway i managed to get in and complete about 75% of the work.
it was agreed that i would fit him in depending on the weather. Each time i book him in it has lashed down.
I wont fix the tiles when its pissing down, and i wont grout the existing fixed tiles either when they are saturated! The customer has removed the tarp saying its the worst thing i could do to cover them up?
I always work to standard, and what i have been taught and learnt by my mistakes.
I have explained my reluctance to finish off the tiles or grout due to the potential issues of trapped water under the tiles, and discolouration and patchy grout, and efflorescence due to the standing water. Am i in the wrong for standing by what i believe to be basic principals of tiling and working to the standards, and should i just crack on with the job regardless?

sorry for the long post but i would be interested to hear what you have to say.

Oh and the customer refused to allow me to erect a canopy over the area to aid in drying and fixing the tiles because they didnt want the house to look like the clampetts house!!
 

Andy Allen

TF
Esteemed
Arms
Reaction score
18,311
Points
1,318
Location
Gloucester
I learnt this lesson a long time ago..... Never ever book in an outside job unless it's the hight of summer..... If there is such a thing in this country..
However I wouldn't of even started the job if it was raining....
Always gets customers backs up if you start something you can't finish...
But yes your right you can't tile or grout in the rain or if the temp is under 5 degrees....
 
B

Bill

I have fixed tiles underwater in swimming pools so I say you do not understand which materials to use to help overcome the situation.
 

Andy Allen

TF
Esteemed
Arms
Reaction score
18,311
Points
1,318
Location
Gloucester
IMG_20171001_160448.png
 

Brian the Tile

TF
Arms
Reaction score
149
Points
973
Location
north wales
Use an appropriate adhesive. Simples. There are quite a few rapid setting adhesives on the market that would be suitable. My preferred choice is from the Ardex range.
Im sorry but i think your answer is crazy ,how the hell can tiling outside steps be compared to patching a couple of tiles in a swimming pool thats comical
 

Reply to Standing my ground and following the codes...Am i in the wrong? in the Canada Tile Advice area at TilersForums.com

There are similar tiling threads here

Good morning all. After a little advice. I'll post pictures a bit later. However.... The...
Replies
6
Views
924
Hi! I'm looking for some advice, I have laid some SLC (Mapei 1210) in our conservatory in...
Replies
5
Views
656
Hi all. Just wanting some advice and wondering what the pros in here are using nowadays for...
Replies
4
Views
687
Hi all! Just wondering what the best advice is for book-keeping? Been self employed now for a...
Replies
1
Views
638
Posting a tiling question to the forum? Post in Tilers' Talk if you are unsure which forum to post in. We'll move it if there's a more suitable forum.
Please visit our sponsor websites, they keep the forum free to use!

Advertisement

New Tiling Questions

Replies you've not seen

Top