Currently reading:
How long to wait until tiling onto 75mm screed

Discuss How long to wait until tiling onto 75mm screed in the Canada Tile Advice area at TilersForums.com.

J

J Sid

Leave 7 days after laying.
Commission ufh and put on low for as long as it takes to dry.
Sand floor to remove latience a few days after heating is turned on ( will set like rock if left any longer) this also helps drying times, a the polymers act like a plastic , trapping moisture.

When it's dry, turn off heating and tile.
sand and cement?
 
S

Spacey

very deep for gypsum based. optimum for those is around 45mm i believe

Yeah doesn't mean it couldn't be though.
It's the most commonly used screed these days over UFH And builders as we know don't always follow the rules.
Could just be a fibre reinforced screed but Id want to be sure what I'm dealing with before laying anything.

In answer to the original question With UFH commissioned and running It's possible to dry it out in about two weeks
 
D

Dumbo

Yeah doesn't mean it couldn't be though.
It's the most commonly used screed these days over UFH And builders as we know don't always follow the rules.
Could just be a fibre reinforced screed but Id want to be sure what I'm dealing with before laying anything.

In answer to the original question With UFH commissioned and running It's possible to dry it out in about two weeks
You shouldn't force dry s&c screed
 

Sean Kelly

TF
Arms
647
1,068
Ruislip
If time is an issue and cost is not an issue then use Ardex A38 (Ultra Rapid Drying Cement for Internal & External Screeds).

Screed the floor and tile after 4 hours. I believe it works out at 1.5 times more than the cost of normal screed.

I have not used this product myself, I got the info from asking the Ardex reps at a trade day.
 
O

Old Mod

If I remember rightly Schluter claim it can be tiled as soon as weight bearing . I stand to be corrected and if I was doing this I would obviously check .


The phrase they like to use is,
'as soon as its mechanically repairable'
Tape the joints for moisture sensitive stone, otherwise not necessary, but certainly doesn't hurt, personally I'd prefer it.
But yes as soon as its load bearing.

To fast track a screed a 'vapour equalisation barrier' must be used i.e.
Ditra 25
Durabase mat

These mats are not for wet ufh obviously, but they still do the same job as above.
Ditra E Heat mat
Variopro ufh mat.
 
O

Old Mod

Is green screed flexible enough for the ufh..?

Maybe not on a green screed.

IMG_0376.PNG

IMG_0378.PNG
 

Reply to How long to wait until tiling onto 75mm screed in the Canada Tile Advice area at TilersForums.com

Posting a tiling question to the forum? Post in Tilers' Talk if you are unsure which forum to post in. We'll move it if there's a more suitable forum.

Advertisement

Top