LOL made sure it was bullet proof but..... in the unlikely event that access is needed, a fitted wardrobe in the spare bedroom backs on to the bath wall, and I will burrow my way in through there !!
 

macten

TF
Esteemed
Arms
Reaction score
1,871
Points
1,158
Location
Nottingham
Okay still got the doors to trim but final bit from me done IMG_0657.JPG
just sparky to sort lights
 
Last edited:

macten

TF
Esteemed
Arms
Reaction score
1,871
Points
1,158
Location
Nottingham
So started rip out in the ensuite today. Tiles didn't come off anywhere near as sweetly as in the bathroom (well not in shower area).

1.JPG

2.JPG

3.JPG

4.JPG

5.JPG

6.JPG

7.JPG

8.JPG

9.JPG

10.JPG

11.JPG
 

macten

TF
Esteemed
Arms
Reaction score
1,871
Points
1,158
Location
Nottingham
So today finally got the 2 bathroom doors trimmed and hung and fitted a couple of bits to the walls. (there's new things everyday that appear and need drilling and fixing :mad:

In the ensuite I've been studding, spragging and making a start on the shower plumbing. Once pb is damaged on metal studding there's just no strength there and it's the only way to go in my opinion. Needed to borrow some room on the RH side for valve placement anyway and I'll nick it back off the LH side when I get that studded tomorrow.

The tray is a crappy foam/plastic one - I did tell them to get a stone resin. Old tray was on a huge riser kit but the fall to the waste is fine for a floor mount so they'll be happy with that.

IMG_0672.JPG IMG_0670.JPG IMG_0669.JPG IMG_0681.JPG IMG_0676.JPG IMG_0678.JPG IMG_0680.JPG
 

macten

TF
Esteemed
Arms
Reaction score
1,871
Points
1,158
Location
Nottingham
First fix plumbing, studding, boarding and tray in.

18.JPG

19.JPG

20.JPG

21.JPG
 
J

Julian 'Farmer' Bonsall

Hi. I notice you use clips and spacers - with some rotated for a smaller gap - is that to just to get a better final finish?
 

macten

TF
Esteemed
Arms
Reaction score
1,871
Points
1,158
Location
Nottingham
I work to a laser line Julian and make tiny adjustments to grout joints if necessary. Spacer in sideways ever so slightly narrows the joint and I usually use wedges if I need to add a little.
 

Reply to Bathroom start to finish in the Canada Tile Advice area at TilersForums.com

There are similar tiling threads here

10 Tiling Tips for Fixing Tiles to Bathroom Walls = From UKTilingForum.co.uk There are a few...
Replies
1
Views
722
    • Like
Bathroom floor. I would be grateful for advice on how to prepare my bathroom sub floor ready for...
Replies
1
Views
499
  • Article
123 Year Old Johnson Tiles Factory to Close Down Causing 110 Job Losses 123 Year Old Johnson...
Replies
9
Views
2K
Hi all! Just wondering what the best advice is for book-keeping? Been self employed now for a...
Replies
1
Views
604
Hi! I'm looking for some advice, I have laid some SLC (Mapei 1210) in our conservatory in...
Replies
5
Views
622
Posting a tiling question to the forum? Post in Tilers' Talk if you are unsure which forum to post in. We'll move it if there's a more suitable forum.
Please visit our sponsor websites, they keep the forum free to use!

Advertisement

New Tiling Questions

Replies you've not seen

Top