You could after 21 days use a green screed adhesive with a vapour equalisation matting. Then tile on the matting to accommodate screed shrinking/ expansion.


I just bought an anti cracking mat and green screed addy in the tile store. They recommended the green screed addy can be used 10-14 days after sand and cement screed is laid.

I have 3 SQ meters to lay although I only got one bag. This should cover the tiles but I'm not sure about both, as in the anti cracking mat and the tiles.

I also have a small patch in the corner needs filled and will be using ardex A29 to fill this in around where the trap is for shower tray. This product, you can tile 24 hours after.
 

Reply to Sand and cement screed down. How long in the General Off-topic Chat (nothing tile) area at TilersForums.com

There are similar tiling threads here

  • Question
I had a small leak in the main water line before the stop tap in my 1950s house. The copper pipe had worn away over the past 70 years, causing a small crack in the copper. A plumber/builder fixed...
Replies
1
Views
805
    • Like
  • Sticky
  • Question
Water Damaged Shower Repairs Shower tile repair – water damage – tile waterproofing Do you have shower leakage that goes downstairs leading to either your main floor or basement? Read this blog...
Replies
0
Views
2K

Advertisement

Birthdays

Top