I have a newly laid screed 75mm thick sand and cement laid 2 weeks ago. I'm stuck for time and need the ensuite floor tiles asap. Is there any products you can recommend for me so I can start laying now rather than wait another few weeks before it's fully dry.
 

average

TF
Reaction score
11
You could after 21 days use a green screed adhesive with a vapour equalisation matting. Then tile on the matting to accommodate screed shrinking/ expansion.


I just bought an anti cracking mat and green screed addy in the tile store. They recommended the green screed addy can be used 10-14 days after sand and cement screed is laid.

I have 3 SQ meters to lay although I only got one bag. This should cover the tiles but I'm not sure about both, as in the anti cracking mat and the tiles.

I also have a small patch in the corner needs filled and will be using ardex A29 to fill this in around where the trap is for shower tray. This product, you can tile 24 hours after.
 

Reply to Sand and cement screed down. How long in the General Off-topic Chat (nothing tile) area at TilersForums.com

Or checkout our tile courses and training forum or the Tile Blog / Latest Blog Posts

This website is hosted and managed by www.untoldmedia.co.uk. Creating content since 2001.



Tile Contractor Forum. The useful tile contractor website.

UK Tiling Forum Stats

Threads
67,365
Messages
881,183
Members
9,531
Latest member
Dawz84
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock    No Thanks