Hi, I am a competent DIYer but would appreciate some professional advice.
Could anyone tell me the correct order in which to lay a loose cable UFH and a BAl rapid Matt?
I have timber floors with existing 20mm floor boards overlaid with ply. Do I lay the UFH then SLC then the decoupling matt or vice versa should the decoupling be installed first and the UFH and SLC onto this then tiles.
if it is the latter should the UFH be stuck directly onto the rapid Matt or onto a layer of https://www.tilersforums.com/forums/tile-adhesive/.
i have seen many contradicting views and would appreciate your help
thanks
Could anyone tell me the correct order in which to lay a loose cable UFH and a BAl rapid Matt?
I have timber floors with existing 20mm floor boards overlaid with ply. Do I lay the UFH then SLC then the decoupling matt or vice versa should the decoupling be installed first and the UFH and SLC onto this then tiles.
if it is the latter should the UFH be stuck directly onto the rapid Matt or onto a layer of https://www.tilersforums.com/forums/tile-adhesive/.
i have seen many contradicting views and would appreciate your help
thanks